Chamette, Louisiana, became to first superstore location in the country to install a new high performance Lafarge ArteviaColor™ integrally colored structural floor. Lafarge personnel worked closely with the project team to ensure the correct color mix, formulation and, most importantly, the correct installation.
The 3,600 cubic yard slab was poured at night when temperatures were cooler and traffic was light. Lafarge went the extra mile to ensure proper sequencing of the 10 separate placements and the curing procedure. The professionalism and expertise of the entire team was an overwhelming success, producing a high profile floor for a high profile customer.